Welded platform for access for pile driving in Puerto Cortés (Honduras)
2013-2014
Grupo FANJUL, S.A.

This project relates to the development of a metal platform for the implementation of pile driving in Honduras, using only two platforms.

Windmill designed the steel structure upon which  a  300T crane will work, with a workload of 99T and a 60m working arm with 20m radius.

We carried out the analysis of the different charge states that result in the construction process (train loads of variable machinery); the design of a platform for cutting container transport; own weight limit for lifting during the progress of the gateway; Unions front and flush cutting.